Domanda di Esame PMP® e CAPM® (C003)
PMI PMP-Prep
Domanda C003
One of the team members on your project wants to increase the estimate of the activity he is working on. He thinks that a risk is almost certain and it will eventually result in more cost. What is the best way to deal with this?
A: Add a buffer to each of the activities in the schedule.
B: Tell your team that you have already estimated for a few buffer days and extra cost, so you are good.
C: Always estimate the activities honestly, and then you can use a contingency reserve to cover for unexpected costs.
D: Fast track the schedule.
Spiegazione
Risposta corretta: C
Il PMBOK a pag. 202 suggerisce di essere onesti nell’effettuare le stime. Perciò anche in questo caso ci dovrebbe essere una riserva per imprevisti.
Mentor
Vito Madaio – certificato PMP® , TSPM™, SMC™, DevOps-Tra®, RWPC™, CSFPC™, membro di PMI® (Project Management Institute) e di IIBA® (International Institute of Business Analysis), A.T.P. di VMedu e ATP di CertiProf®, con oltre 40 anni di esperienza maturata in ambienti internazionali come: IBM Italia, Skandia Italia, Capgemini, TenStep e attualmente PMTSI.
Contattaci per un’edizione assistita a distanza per professionisti della tua azienda