One of the team members on your project wants to increase the estimate of the activity he is working on. He thinks that a risk is almost certain and it will eventually result in more cost. What is the best way to deal with this?

A: Add a buffer to each of the activities in the schedule.
B: Tell your team that you have already estimated for a few buffer days and extra cost, so you are good.
C: Always estimate the activities honestly, and then you can use a contingency reserve to cover for unexpected costs.
D: Fast track the schedule.

Spiegazione

Risposta corretta: C

Il PMBOK a pag. 202 suggerisce  di essere onesti nell’effettuare le stime. Perciò anche in questo caso ci dovrebbe essere una riserva per imprevisti.

Mentor

Vito Madaio – certificato  PMP® , TSPM™, SMC™,  DevOps-Tra®, RWPC™, CSFPC™, membro di PMI® (Project Management Institute) e di IIBA® (International Institute of Business Analysis),  A.T.P. di VMedu e ATP di CertiProf®, con oltre 40 anni di esperienza maturata in ambienti internazionali come:  IBM Italia,  Skandia Italia, Capgemini, TenStep e attualmente PMTSI.

Vito Madaio - PMP Instructor

Contattaci per un’edizione assistita a distanza per professionisti della tua azienda

Formazione Project Manager, Business Analyst, Risk Manager, Web Marketing