Which of the following is not used to determine the duration estimate of each activity?

A: Milestone list
B: Activity list
C: Activity attributes
D: Basis of estimate

Spiegazione

Refer to PMBOK Guide – Sixth Edition, pag. 195.

This question is indirectly asking you which of the options is not an INPUT to estimate activity duration process.

Option D is the correct choice as the basis of estimate is an OUTPUT.

Il Nuovo Esame PMP® NON si basa solo  sul PMBOK ® Guide, ma piuttosto sul programma di esame pubblicato in:  “The PMP Examination Content Outline“, ripreso e  illustrato nella fase di orientamento iniziale di questo corso.

Mentor

Vito Madaio – certificato  PMP® , TSPM™, SMC™,  DevOps-Tra®, RWPC™, CSFPC™, membro di PMI® (Project Management Institute) e di IIBA® (International Institute of Business Analysis),  A.T.P. di VMedu e ATP di CertiProf®, con oltre 40 anni di esperienza maturata in ambienti internazionali come:  IBM Italia,  Skandia Italia, Capgemini, TenStep e attualmente PMTSI.

Vito Madaio PMP Instructor 2024